Construction Works – Starting Friday 22 May
SITE PLAN
We would like to inform all members about the forthcoming construction works and what to expect on site.
Tennis Access Changes
- Court 3 will be closed on Friday 22 May to allow completion of a new access path. (Number 1 on the map) There will be full access to tennis court 3 throughout the construction period.
- This new path will run from the dome side fire exit, around the back of the dome, and into Court 3 via a newly installed gate.
- This route is outside of the construction area and will provide a safe access point for tennis players.
Please note:
- A secure fence will separate the construction zone, which is restricted to authorised staff only.
- Additional fencing will prevent access beyond the dome door, making the new rear gate the only entry point for Court 3.
Site Traffic & Parking Disruption (Friday 22 May)
- There may be short-term disruption on the road passing the Kids Zone (crèche) due to delivery and positioning of a portacabin.
- Exact timings will be communicated once confirmed.
- Parking spaces directly in front of the dome and opposite will be closed for construction staff use. (Number 2 on the map)
Golf Course Access & Safety
- A designated path to the 8th tee will be introduced and clearly signposted. (Number 3 on the Map)
- Fencing will be installed near the 9th hole—please take extra care when playing shots in this area.
- The site will operate under a strict hard hat policy at all times.
For play adjustments:
- A drop zone for affected shots will be marked out next week by the Golf Professionals and Head of Grounds.
- New path exiting Hole 9 joining up to the path to the Sports Complex front door. (Number 4 on the map)
- Further details on its exact location will follow shortly.
Safety First
We kindly ask all members to:
- Follow all signage and instructions
- Respect restricted areas
- Exercise extra caution around construction zones
Your safety, and that of our staff and contractors, is our top priority and any issues you come across please report them to the Complex Main Reception.
Thank you for your cooperation and understanding while we carry out these improvements.